Template:RiskAssessment/Mains: Difference between revisions
From SUWS-wiki
(Created page with "<noinclude> Risks associated with the use of mains power outside {{RiskAssessment/RiskMatrix}} {| class="wikitable" {{RiskAssessment/Columns}} </noinclude> ! colspan=7 | Mains Po...") |
(Update to 2020 Risk Assessment Format) |
||
(2 intermediate revisions by one other user not shown) | |||
Line 1: | Line 1: | ||
<noinclude> | <noinclude> | ||
Risks associated with the use of mains power outside | Risks associated with the use of mains power outside | ||
{{RiskAssessment/ | {{RiskAssessment/RiskMatrix2020}} | ||
{| class="wikitable" | {| class="wikitable" | ||
{{RiskAssessment/ | {{RiskAssessment/Columns2020}} | ||
</noinclude> | </noinclude> | ||
! colspan= |   | ||
|- | |||
! colspan="11" | Mains Power | |||
|- | |- | ||
| Mains electricity | | Mains electricity | ||
| Electric shock or electrocution | | Electric shock or electrocution | ||
| Users | |||
| 3 | |||
| 5 | |||
| 15 | |||
| Ensure that mains-powered equipment has recently been safety tested. Ensure that appropriately IP-rated equipment is used for outdoor installations. | | Ensure that mains-powered equipment has recently been safety tested. Ensure that appropriately IP-rated equipment is used for outdoor installations. | ||
| | | 1 | ||
| | | 5 | ||
| | | 5 | ||
| | | | ||
<noinclude> | <noinclude> | ||
|} | |} | ||
</noinclude> | </noinclude> | ||
<noinclude>[[Category:Risk Assessment Template]]</noinclude> |
Latest revision as of 23:33, 29 August 2020
Risks associated with the use of mains power outside
Impact | ||||||
---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | ||
Likelihood | 1 | 1 | 2 | 3 | 4 | 5 |
2 | 2 | 4 | 6 | 8 | 10 | |
3 | 3 | 6 | 9 | 12 | 15 | |
4 | 4 | 8 | 12 | 16 | 20 | |
5 | 5 | 10 | 15 | 20 | 25 |
Liklihood | Description | |
---|---|---|
1 | Rare | 1 in 100,000 chance |
2 | Unlikely | 1 in 10,000 chance |
3 | Possible | 1 in 1,000 chance |
4 | Likely | 1 in 100 chance |
5 | Very Likely | 1 in 10 chance |
Impact | Description | |
---|---|---|
1 | Trivial/Insignificant | Very Minor injuries e.g. slight bruising |
2 | Minor | Injuries or illness e.g. small cut or abrasion which require basic first aid treatment even if self administered |
3 | Moderate | Injuries or Illness e.g. straining or sprain requiring first aid or medical support |
4 | Major | Injuries or illness e.g. broken bones requiring medial support > 24 hours and time off work or study > 4 weeks. |
5 | Severe/Extremely Significant | Fatality or multiple serious injuries or illness requiring hospital admission or significant time off work or study. |
Hazard | Potential Consequences | Persons at Risk | Inherent | Control Measures | Residual | Further Controls | ||||
---|---|---|---|---|---|---|---|---|---|---|
Likelihood | Impact | Score | Likelihood | Impact | Score
| |||||
Mains Power | ||||||||||
Mains electricity | Electric shock or electrocution | Users | 3 | 5 | 15 | Ensure that mains-powered equipment has recently been safety tested. Ensure that appropriately IP-rated equipment is used for outdoor installations. | 1 | 5 | 5 |